Expansion & Renovation


Expanded/Renovated Henderson Library Overview

What the future holds:August 2006

The estimated completion date is fall 2008.

The expanded/renovated Library will be almost double the size of the original building.

The new automated retrieval system will be the first of its kind in the southeast.

What happens summer 2006 through fall 2008:

Phase two of construction (four story western addition and renovation of old building) is estimated to be completed during the fall of 2008.

Library services and collections will be available in the new eastern addition.

Current and recent bound periodicals and some books will be also housed on the second and third floors. The reference collection and the Information Services Librarians will be housed on the third floor.

The first floor will contain some non-computer seating, a multipurpose classroom, and two computer classrooms with 30 computers each.

Less heavily used materials will be housed in the automated retrieval collection during the two years of phase two, and items will be delivered to users at the Circulation Desk when requested.

Less used materials will be stored off campus, and will require longer to retrieve than those on campus – perhaps 24 hours or more.

The number of seats available within the Library will be reduced but computers and study areas will be available in other buildings on campus. Library electronic resources will be available from any computer connected to the campus network. For example, additional computer access will be provided in the College of Information Technology.

The three story glass atrium will be available for scheduling campus events if they do not interfere with the Library’s mission of ensuring a comfortable and responsive study environment.